Annual Road Program
Each year, the Department of Public Works reviews street conditions to develop its annual road reconstruction program. The program is based on a number of factors such as street and sidewalk conditions as well as past and planned utility work. The proposed program is presented to the City Council Committee on Public Works, which then reviews and makes recommendations to the entire City Council.
2026 Annual Road Program
This section is being updated. Check back soon for more information.
2026 Annual Road Program Public Works Subcommittee Presentation - October 22, 2025 (PDF)
Complete Streets
Projects within the Annual Road Program involve substantial reconstruction and improvement of the road surface, sidewalks, and associated infrastructure. The City uses these necessary reconstructions as opportunities to incorporate Complete Streets design principles and infrastructure in accordance with the City's Complete Streets Prioritization Plan. The improvements include repaving and re-striping, new granite curbing, traffic flow and safety enhancements, stormwater management infrastructure, and beautification. More information on Complete Streets design and benefits can be found on the Complete Streets page. Many of these streets have already undergone substantial utility work in preparation for road reconstruction.
The road reconstruction projects happening throughout the 2026 construction season are broken up into three phases. Phases have been determined by previous allocations of funding throughout the past several fiscal years.
Fiscal Year 2026 — Phase 1
Newport Construction Corporation will be working on the streets included in Phase 1 of the Annual Road Program, and Bobrek Engineering completed the design/engineering plans.
For up-to-date information about active projects, view the most recent abutter notice(s). Project-specific information and dates will be sent to affected abutters at least 5 days before the start of work. All dates and durations are estimates and subject to change due to weather or unforeseen circumstances.
| Street | Status | Expected Start Date | Expected End Date | Plan/Design | Abutter Notice(s) |
|---|---|---|---|---|---|
| George Street | Not started | Mid-June | Late August | George Street Plans | |
| Bromfield Street | Active | May 4, 2026 | Late June | Bromfield Street Plans | Mobilization Notice, Complete Streets Notice |
| Mangano Court | Not started | Early September | Early October | Mangano Court Plans | |
| Grandview Avenue | Not started | TBD | TBD | Grandview Ave Plans | |
| Dwight Street | Not started | Early October | Mid-December | Dwight Street Plans |
Fiscal Year 2026 — Phase 2
Bobrek Engineering completed the design/engineering plans for the streets included in Phase 2 of the Annual Road Program. The contract is currently out to bid, and a contractor has not yet been selected.
For up-to-date information about active projects, view the most recent abutter notice(s). Project-specific information and dates will be sent to affected abutters at least 5 days before the start of work. All dates and durations are estimates and subject to change due to weather or unforeseen circumstances.es.
| Street/Project | Status | Expected Start Date | Expected End Date | Plan/Design | Abutter Notice(s) |
|---|---|---|---|---|---|
| Pequossette Street | Not started | TBD | TBD | ||
| N. Irving Park | Not started | Early October | Mid-December | ||
| S. Irving Park | Not started | Early October | Mid-December | ||
| Royal Street | Not started | Early October | Mid-December | ||
| Green Street | Not started | Early June | Mid-October |
Fiscal Year 2026 — Phase 3
Horsely Witten Group is currently working on the final design/engineering plans for the streets included in Phase 3 of the Annual Road Program. The contract will go out to bid by July 1, 2026.
For up-to-date information about active projects, view the most recent abutter notice(s). Project-specific information and dates will be sent to affected abutters at least 5 days before the start of work. All dates and durations are estimates and subject to change due to weather or unforeseen circumstances.
| Street/Project | Status | Expected Start Date | Expected End Date | Plan/Design | Abutter Notice(s) |
|---|---|---|---|---|---|
| Cottage Street | Design phase | TBD | TBD | ||
| Sawin Street | Design phase | TBD | TBD | ||
| Rifle Court | Design phase | TBD | TBD | ||
| Lyons Street | Design phase | TBD | TBD | ||
| Sexton Street | Design phase | TBD | TBD | ||
| Cottage Lane | Design phase | TBD | TBD | ||
| Molloy Street | Design phase | TBD | TBD | ||
| Hearn Street | Design phase | TBD | TBD | ||
| Winter Street | Design phase | TBD | TBD |
Short Streets and Connectors
Short Streets and Connectors are smaller street sections that provide connections to higher-volume transit corridors. There are not currently any ongoing or imminent short streets and connectors projects.
Long Streets and Collectors
Long streets and collectors projects are longer stretches of roads or important road sections that see a high volume of vehicle traffic and are undergoing full reconstruction and redesign. These projects are typically more time-intensive, and the end-resulting roads use Complete Streets design elements. This includes granite curbing, new sidewalks, ADA-compliant ramps/curb cuts, beautification elements, traffic calming measures, and stormwater management infrastructure. During these construction projects, residents can expect substantial impacts such as full road closures and detours, as the process involves utility work, sidewalk work, and full road resurfacing and redesign using heavy machinery.
Further communication will be provided to affected abutters for each project, but residents should always allow for more time when navigating areas that are included in Long Streets and Connectors projects.
For up-to-date information about active projects, view the most recent abutter notice(s). Project-specific information and dates will be sent to affected abutters at least 5 days before the start of work. All dates and durations are estimates and subject to change due to weather or unforeseen circumstances.
| Street/Project | Status | Expected Start Date | Expected End Date | Contractor | Plan/Design | Abutter Notice(s) |
|---|---|---|---|---|---|---|
| Forest Street & Springfield Street (1900 linear feet) | Not started | Early June | Fall 2027 | A.R. Belli, Inc. | ||
| Fifth Avenue (550 linear feet) | Active | April 20, 2026 | Late November | Charles Contracting Co. | Fifth Ave Plans, Fifth Ave Design | Valve Cut-in Notice, Water Bypass Notice, Mobilization Notice |
Grant Funded Projects
| Street/Project | Status | Expected Start Date | Expected End Date | Plan/Design | Abutter Notice(s) |
|---|---|---|---|---|---|
| Dexter Avenue | Active | April 21, 2026 | End of June | Dexter Ave Design, Dexter Ave Plans | Abutter Notice |
| Templeton Parkway | Active | May 11, 2026 | Early September | Templeton Pkwy Designs, Templeton Pkwy Plans | Abutter Notice |
Milling and Overlay
Milling and overlay is a process that extends the life of roadways without requiring a full-depth reconstruction. This process is used on roads where the surface is deteriorating, but the sub-surface materials still have substantial integrity. First, crews mark out the extent of the work and all utility infrastructure—this stage of the process should not disrupt traffic or impact residents. Then, the top 1.5" of the pavement is milled off and replaced with new layers of asphalt, resulting in a smoother roadway than pavement patches.
This process is usually used on shorter stretches of road up to 500 feet in length, and it is more cost- and time-effective than a full reconstruction. The work takes 3-5 days to complete, and residents can expect intermittent lane closures and detours. Typically, at least one lane will remain open to vehicle travel during this process, and police details are present to direct traffic.
Newport Construction Corporation will be conducting the milling and overlay work throughout the 2026 road construction season.
For up-to-date information about active projects, view the most recent abutter notice(s). Project-specific information and dates will be sent to affected abutters at least 5 days before the start of work. All dates and durations are estimates and subject to change due to weather or unforeseen circumstances.
| Street | Limits | Expected Start Date | Status | Abutter Notice(s) |
|---|---|---|---|---|
| York Avenue | Belmont Street to Lowell Avenue | Not started | ||
| Hall Avenue | Belmont Street to Fairview Avenue | Not started | ||
| Hardy Avenue | Belmont Street to Fairview Avenue | Not started | ||
| Warwick Road | Belmont Street to Fairview Avenue | Not started | ||
| Langdon Avenue | Belmont Street to Maplewood Street | April 27, 2026 | Complete | Mill & Overlay Notice, Paving Notice |
| Winsor Avenue | Mount Auburn Street to Maplewood Street | April 27, 2026 | Complete | Mill & Overlay Notice, Paving Notice |
| Coolidge Hill Road | Grove Street to 81 Coolidge Hill Road | April 27, 2026 | Complete | Mill & Overlay Notice, Paving Notice |
| Coolidge Hill Road | Arlington Street to Kondazian Street | April 27, 2026 | Complete | Mill & Overlay Notice, Paving Notice |
| Gilbert Street | Highland Avenue to Main Street | Not started | ||
| Charles Street | Gilbert Street to Olney Street | Not started | ||
| Olcott Street | Highland Avenue to Main Street | Not started | ||
| Prescott Street | Charles Street to Main Street | Not started | ||
| Gleason Street | Highland Avenue to Main Street | Not started | ||
| Marshall Street/Oliver Street | Sydney Street to Church Street | Not started | ||
| Franklin Street | Mount Auburn Street to Walnut Street | June 1, 2026 | In progress | Milling & Overlay Notice |
| Center Street | Franklin Street to Walnut Street | June 1, 2026 | In progress | Milling & Overlay Notice |
| Walnut Street | Center Street to Birch Road | June 1, 2026 | In progress | Milling & Overlay Notice |
| Flint Road | School Street to Dead End | June 1, 2026 | In progress | Milling & Overlay Notice |
| Gay Road | Flint Road to Sunnybank Road | June 1, 2026 | In progress | Milling & Overlay Notice |
| Cleveland Road | Warren Street to Jefferson Road | Not started | ||
| Morrison Road | Warren Street to Jefferson Road | Not started | ||
| Copeland Street | Main Street to Highland Avenue | Not started | ||
| Philip Darch Road | Lexington Street to Rose Avenue | Not started | ||
| Robert Ford Road | Lexington Street to Philip Darch Road | Not started | ||
| King Street | Warren Street to Madison Avenue | Not started | ||
| Hersom Street | Main Street to Highland Avenue | Not started |
Past Annual Road Programs
2025 Annual Road Program
2025 Annual Road Program Public Works Subcommittee Presentation - October 28, 2024
2024 Annual Road Program https://www.watertown-ma.gov/asset/e7545088-480e-4fc9-ad79-2cec78c9d396
- Bromfield Street, Grandview Avenue, Mangano Court, Dwight Street and George Street have been selected for full reconstruction as part of the City’s 2024 Annual Road Program. Roadway reconstruction entails removing and replacing the existing roadway, regrading of the road, and rehabilitation of the roadway base. Per City Council directive, roads that undergo full reconstruction also receive granite curb installation, new concrete sidewalks and driveway aprons, and ADA-compliant accessible ramps.
2024 Annual Road Program Public Works Subcommittee Presentation - November 16, 2023
2023 Annual Road Program
Francis Street, Bates Road, Bates Road East, Bradshaw Street, Essex Street, and Nash Street have been selected for full reconstruction as part of the City’s 2023 Annual Road Program. Roadway reconstruction entails removing and replacing the existing roadway, regrading of the road, and rehabilitation of the roadway base. Per City Council directive, roads that undergo full reconstruction also receive granite curb installation, new concrete sidewalks and driveway aprons, and ADA-compliant accessible ramps.
Schedule Updates:
- https://content.civicplus.com/api/assets/3003c75f-7838-4b12-ab39-7eac8fb76a03 Week of May 8
- Week of April 17
Additional Information:
- Frequently Asked Questions
- Francis Street: Neighborhood Letter
- Bates Road/Bates Road East
- Bradshaw Street: Neighborhood Letter
- Nash Street/Essex Street
Additional Documents:
- Watertown Climate and Energy Plan
- Community Greening Program
- Watertown Complete Streets Policy
- Tree Request Form
- Residential Driveway Information https://portal.laserfiche.com/Portal/DocView.aspx?id=17445&repo=r-5ece5628
- Guide to the Planting Strip https://www.watertown-ma.gov/asset/62bfe825-62cd-4401-9d7e-300a9b9b2a9d
- Winter Maintenance and Deicing https://portal.laserfiche.com/Portal/DocView.aspx?id=17428&repo=r-5ece5628
- Presentation to City Council Committee on Public Works, November 1, 2022 https://portal.laserfiche.com/Portal/DocView.aspx?id=17429&repo=r-5ece5628
- List of 2022 Work Completed (to November 1, 2022)
2022 Annual Road Program
The following streets have been selected for full reconstruction as part of the City’s 2022 Annual Road Program. Roadway reconstruction entails removing and replacing the existing roadway, regrading of the road, and rehabilitation of the roadway base. Per City Council directive, roads that undergo full reconstruction also receive granite curb installation, new concrete sidewalks and driveway aprons, and ADA-compliant accessible ramps.
- Chester Street: Concept Plan | Neighborhood Letter
- Locke Street: Concept Plan | Neighborhood Letter
- Boylston Street--Fairfield Street to Porter Street: Concept Plan | Neighborhood Letter
- Chapman Street--Main Street to Grandview Ave.: Concept Plan | Neighborhood Letter (Note: This project will be constructed in conjunction with the Highland Ave. project) | Parking Plan Update--#49 to #67 | Parking Plan Letter--#49 to #67 | Traffic Commission Mintues
Additional Information:
- Residential Driveway Information https://portal.laserfiche.com/Portal/DocView.aspx?id=17445&repo=r-5ece5628
- Guide to the Planting Strip https://www.watertown-ma.gov/asset/62bfe825-62cd-4401-9d7e-300a9b9b2a9d
- Winter Maintenance and Deicing (PDF) https://portal.laserfiche.com/Portal/DocView.aspx?id=17447&repo=r-5ece5628
- Presentation to Town Council Public Works Subcommittee on October 18, 2021
2021 Annual Road Program
The following streets have been selected for full reconstruction as part of the Citys 2021 Annual Road Program. Roadway reconstruction entails removing and replacing the existing roadway, regrading of the road, and rehabilitation of the roadway base. Per Town Council directive, roads that undergo full reconstruction also receive granite curb installation, new concrete sidewalks and driveway aprons, and ADA-compliant accessible ramps.
Alden Road: Concept Plan | Neighborhood Letter
Elmwood Ave: Concept Plan | Neighborhood Letter
Gertrude Street: Concept Plan | Neighborhood Letter
Goldie Street: Concept Plan | Neighborhood Letter
Grandview Ave (Copeland Street to Chapman Street): Concept Plan | Neighborhood Letter
Hazel Street (Quimby Street to Dexter Ave): Concept Plan | Neighborhood Letter
Sheldon Road: Concept Plan | Neighborhood Letter
Residential Driveway Information
Winter Maintenance and Deicing
Presentation to Public Works Subcommittee September 24, 2021
2020 Annual Road Program
Scope of Work
Full Depth Reconstruction (curbs, grass strip and sidewalks included):
- Downey Street (Map)
- Frank Street & Louise Street (Map)
- Kimball Road (Map)
- Piermont Street & Tappan Avenue (Map)
- Wheeler Lane (Map)
Presentation to Public Works Subcommittee August 22, 2019
Residential Driveway Information
2019 Annual Road Program
Full Depth Reconstruction (curbs, grass strip and sidewalks included):
- Bellevue Road (Channing Road to Common Street) (Map)
- Avon Road (Map)
- Chandler Street (Map)
- Burnham Street (Map)
- Bridgham Avenue (Map)
- Nichols Avenue (Dexter Avenue to Boylston Street) (Map)
- Bartlett Street (including Everett Ave.) (Map)
Presentation to Public Works Subcommittee December 18, 2018
2018 Annual Road Program
Full Depth Reconstruction (curbs, grass strip and sidewalks included):
- Edgecliff Road
- Westland Road and Woodleigh Road
- Everett Avenue (Bartlett to Palfrey)
- Malden Street
- Priest Road
- Arden Road
2019 Road Presentation Priest Road
Presentation To Public Works Subcommittee October 18, 2018
2017 Annual Road Program
Full Depth Reconstruction (curbs, grass strip and sidewalks included):
- Hovey Street
- Cushman Street
- Waltham Street(Rosedale Road to Bridge Street)
- Knowles Road, including Holly Street and Whitcomb Avenue
- Irma Avenue
Presentation To Public Works Subcommittee October 27, 2016
2016 Annual Road Program
Full Depth Reconstruction (curbs, grass strip and sidewalks included):
- Edenfield Avenue( Main to Waverly)
- Hillside Road (Belmont Street to Hillcrest Circle)
- Hillcrest Circle
- Grenville Road
- Merrill Road
- Purvis Street